Container Guest House 11 30 2011

Container Guest House [DAY 23] 11302011

Placement + Connection

Nov. 30 was an important milestone in the course of this project. On this day, all bits and pieces of this simple but elegant vessel converged on the site.

The crane was in position at noon, and shortly afterwards the second half of the container arrived.

Ropes were used to rotate and align containers to their correct positions. After both containers were set in place, John Andrews, the project welder, joined the footings of both containers to embedded steel plates.

The alignment and welding process took roughly 3 hours.

 

 

 

 

John Andrews, the welder, connecting a footing of the container to a previously installed 6×6 Dia hook.